Data / Renewables · Germany

Renewable buildout by region

All 6,574,299 solar, wind, biomass and hydro units in operation in the official register, plus the pipeline. Filter by technology, size, region, operator, grid level and more, in net or gross capacity; every view can be shared as a link or downloaded as CSV.

Source
Marktstammdatenregister, BNetzA
Export
17 Nov 2026
Coverage
6,574,299 units · 215.9 GW net · 231.4 GW gross in operation
Refresh
Weekly, automatic

Open data: Download these tables (Parquet, CSV) on Hugging Face

Key insights · 17 Nov 2026

What the register says

  • Solar · January to November 202615.1 GW

    of solar (module peak) was commissioned this year, down 5% on the same months of 2025. Ground-mounted parks are 52% of it.

    See solar this year →
  • Onshore wind · January to November 20264.71 GW

    of onshore wind went into operation this year, up 6% on the same months of 2025, from 879 turbines averaging 5.4 MW.

    See onshore wind →
  • Fields versus roofs52%

    of new solar capacity in 2026 is ground-mounted, against 29% in 2020. Rooftop additions in 2025 were down 23% on 2023.

    Compare solar segments →
  • Balcony solar1,561,194

    plug-in solar units are registered, 358,575 of them in 2026: 46% of all new solar units, but only 2.1% of new solar capacity.

    See balcony solar →
  • Solar plus storage79%

    of new rooftop systems under 30 kW in 2026 have a battery registered on site, against 53% in 2020. Home solar is now mostly sold with storage.

    See rooftop solar with batteries →
  • A north–south split62%

    of onshore wind capacity stands in five northern and eastern states (Niedersachsen, Schleswig-Holstein and others), while Bayern and Baden-Württemberg host 39% of all solar but only 7% of onshore wind.

    Open the map →
  • Offshore wind11.7 GW

    of offshore wind is in operation in the North and Baltic Seas. 1.96 GW of it, in 143 turbines, was commissioned in 2026.

    See offshore parks →
  • Wind pipeline54.0 GW

    of onshore wind is registered as in planning (8,736 turbines), 75% of today’s onshore fleet. Permitted turbines must be registered, so wind’s pipeline is better covered than solar’s.

    Open the pipeline →
  • Turbine makers · 202531%

    of new onshore wind capacity in 2025 came from Nordex. The top three makers supplied 91%.

    See turbine makers →
  • Read recent months with care81 days

    pass before 90% of rooftop solar units are registered (median 8 days); for onshore wind it is 22 days. The latest two months always look weaker than they will end up.

    See this year →

Explorer

Slice the buildout

Loading the register data…

Method

How these numbers are built

  1. Pull

    Every Monday a scheduled job reads the needed files of the MaStR full export from the BNetzA server: solar, wind, biomass and hydro units, their EEG records, grid connection points and market actors.

  2. Join

    Each unit gets its grid connection (voltage level, grid operator), its operator type (organisation names only; private persons stay anonymous) and, from 300 kW, whether it won an EEG tender.

  3. Clean

    In operation (including temporarily shut down) or in planning. Left out: 7 without capacity, 68 with implausible capacity, 0 in operation without a commissioning date. Units shut down for good only feed the history chart.

  4. Classify

    Solar type as registered (building, ground-mounted, plug-in), wind on land or at sea. Places from the official municipality key, mapped to the district boundaries of 1 Jan 2026; offshore wind sits in the exclusive economic zone.

  5. Net or gross

    Net rated power (Nettonennleistung) is the grid-side output; gross (Bruttoleistung) the generator or module rating. For solar, gross is the module peak power used in BNetzA’s headline statistics; net is capped by the inverter.

Data: Bundesnetzagentur, Marktstammdatenregister, export of 17 Nov 2026, licensed under Datenlizenz Deutschland – Namensnennung – 2.0. Boundaries © GeoBasis-DE / BKG 2026 (data changed); © Statistisches Bundesamt (Destatis). Recent months are incomplete because of late registrations. Planned units are only those registered early. Scripts: scripts/data/. Built 2026-11-18.

Validation

Checked against the official statistics

Gross capacity in operation at the end of September 2026, from this explorer’s data, against the BNetzA, EE-Statistik September 2026 (MaStR evaluated 13 Oct 2026) (gross, including temporarily shut-down units, registered units only). Our export is newer, so late registrations add a little.

TechnologyThis explorer, MWBNetzA, MWDifferenceThis explorer, unitsBNetzA, unitsDifference
Solar, total131,139130,675+0.4%6,411,6506,395,688+0.2%
Solar, building-mounted82,43282,200+0.3%4,862,0784,846,106+0.3%
Solar, ground-mounted46,98146,746+0.5%19,97019,834+0.7%
Solar, plug-in (balcony)1,6671,671−0.3%1,529,4681,529,612−0.0%
Onshore wind71,19971,267−0.1%30,44030,494−0.2%
Offshore wind11,59911,539+0.5%1,8151,811+0.2%
Biomass9,1959,264−0.7%22,03222,067−0.2%

Hydropower is not in BNetzA’s monthly statistic; AGEE-Stat reports about 5.4 GW for the end of 2025, including pumped storage with natural inflow. BNetzA’s “Nettozubau” means additions minus final shutdowns, still in gross capacity, not net rated power.

Glossary

What the labels mean

Units
Registered generating units. One rooftop system is usually one unit; a wind park has one unit per turbine.
Net capacity
Net rated power (Nettonennleistung): the maximum continuous output at the grid side. For solar it is capped by the inverter.
Gross capacity
Gross power (Bruttoleistung): the generator or module rating. For solar this is the module peak power (kWp), the basis of BNetzA’s headline figures.
Gross ÷ net
Gross divided by net capacity. Solar arrays are often sized above their inverter, so the ratio is above 1.
In planning
Units registered with the status “in planning”. Registration before commissioning is optional for most units, so the real pipeline is larger; not every project will be built. Wind is better covered.
Registration lag
Days between commissioning and registration. The latest months always look weaker than they will end up.
Bundesland
Federal state, from the official municipality key of the unit. Offshore wind sits in the exclusive economic zone (EEZ) and is its own row.
Operator type
Who runs the unit. Organisations include companies, utilities, cooperatives and municipalities. Private persons stay anonymous in the register.
Feed-in mode
Self-consumption first: the site uses its own power and exports the surplus. Full feed-in: all output goes to the grid.
Remote control
Whether the grid operator and/or a direct marketer (for example a virtual power plant) can control the unit remotely, as registered.
Voltage level
Grid level of the connection point. Rooftop solar connects at low voltage; parks and wind farms at medium, high or extra-high voltage.
Tender award
The unit won a federal EEG tender (Ausschreibung). Tenders apply from 750 kW for solar and to almost all new wind; smaller units get a fixed feed-in tariff.
Usage sector (solar)
Where the solar system is used, as registered: households, commerce & services, industry, agriculture, public buildings. Solar only.
Orientation (solar)
Main direction the modules face. East-west systems produce a flatter daily profile; south maximises yearly output. Solar only.
Battery on site (solar)
Whether a battery is registered at the same location as the solar system. Solar only.
Turbine maker (wind)
Manufacturer as registered, with predecessors merged into today’s brands (REpower → Senvion; Tacke, Enron Wind → GE; Siemens, Gamesa, Bonus, Adwen → Siemens Gamesa; NEG Micon → Vestas). Wind only.